Lismore City Hall – In Progress
The inside of Lismore City Hall was severely impacted by the 2022 natural disaster. To restore the landmark building, early works including internal demolition and detailed internal design were undertaken in early 2024.
Funding |
Co-funded by Create NSW and the Australian and NSW Government disaster recovery authorities |
Status |
In progress |
Timeframe |
Estimated completion early 2026 |
Disaster |
AGRN1012 |
Once restoration works are completed in early 2026, Lismore City Hall will restore a missing piece of the regional social landscape, as it once again hosts an enticing mix of performing arts and cultural events.
See below for project updates.

February 2025
Site establishment is complete with some early works having commenced, including internal rendering, roof works on the western side of the building and plumbing.


January 2025
The project recommenced after funding was received in December 2024. The reinstatement of funding has meant that works are now able to recommence, with site establishment underway. Full restoration of the facility will commence in late February and is expected to take approx. 12 months. This restoration includes the installation of internal floors, ceilings, walls, bathrooms, staging and seating.
November 2024
The project was placed on hold due to lack of funding.
August 2024
City Hall experienced a series of enabling works, but progress has been curtailed due to funding constraints. Despite the site's demobilization, detailed designs and a comprehensive cost plan for its restoration and improvement have been completed and received. Council is working with various State Government funding agencies to commence Stage 2 (construction and refurbishment) as soon as possible.
July 2024
Early works at the Lismore City Hall site included completing Stage 1 footings and blockwork, which were core-filled. The setup of stage 2 footings, columns and block walls, along with the installation of structural beams, progressed.
Adjustments to props allowed for the next stages of work, with blockwork and column installations completed by late June. Stage 1 has been successfully completed, with preparations underway for the initiation of Stage 2.

May 2024
Asbestos removal (windows) to the western façade and the north elevation (D1.02) were completed by the middle of May 2024. Demolition was also completed by mid-May 2024 with the installation of footings, columns and block work for prop removal (Level 1 internal).
Roof leaks were repaired above the stage. Hoardings were installed where the windows had been removed. Load bearing walls were removed where required, with footings being exposed and geotechnical investigations undertaken to firm up footing design. Demolition works at Lismore City Hall.